Public Works

Western Gateway

Project overviewWestern Gateway closure
Western Gateway will revitalize West Railroad Avenue from Pacific Court at the Shelton city limits through the intersection with 8th Street. Prior to construction, city crews will remove the railroad tracks that cross Railroad Avenue near the 11th Street intersection.

Specific improvements coming as part of this project include:
  • New pavement
  • Storm drain improvements
  • New water main and water services
  • New curb, gutter, and sidewalks
  • New bus pullout with bus shelter
project timeline
In 2018, we first applied for grant funding and initiated the design process for Western Gateway. In 2019, we held a design concept public meeting (Click here to view design concept public meeting slides). We have finished the design process and will be going out to bid for Western Gateway very soon. Construction is expected to begin spring 2022.Western Gateway timelinetraffic revisions
This project will have traffic impacts. We will provide advanced notification of traffic revisions as needed. Be sure to either bookmark this webpage, or follow the City of Shelton on Facebook, Twitter, or download our mobile app for the latest updates.

Project budget
The total project budget is $2.6 million, funded in part by the Transportation Improvement Board and the American Rescue Plan Act.

Project documents
project contact
Ken Gill
City Engineer
ken.gill@sheltonwa.gov
360-490-0453